Politics

Jacksonville Gets a 1-Year Data Center Moratorium Bill Tuesday: What It Pauses, Who Is Exempt and Why Duval Would Be 4th in the Region

A close-up of the back of a server rack, the kind of equipment data centers hold; this rack is in a California research center, not in Jacksonville.

A close-up of the back of a server rack, the kind of equipment data centers hold; this rack is in a California research center, not in Jacksonville. Photo: Derrick Coetzee from Berkeley, CA, USA / Wikimedia Commons (CC0)

JACKSONVILLE, Fla. - A bill that would stop Jacksonville from accepting, reviewing or approving data center applications for one year is scheduled to be introduced at Tuesday's City Council meeting, according to Jacksonville Today. Council members Jimmy Peluso and Moné Holder are sponsoring the pause, which they say would give the city time to write zoning and safety rules before any large data center arrives. If it passes, Duval would become the fourth Northeast Florida county with a moratorium, after St. Johns, Nassau and Clay.

What would the bill actually do?

The proposal would pause the acceptance, review and approval of data center development applications for one year, Jacksonville Today reported Nov. 19. It would not apply to data centers that already exist or to expansions that have already been approved. The stated goal is to give the city time to draft new zoning and safety policies for future hyperscale data centers, the very large facilities that serve cloud computing and artificial intelligence.

During the pause, a task force of city staff would study best practices, according to the bill as described by Jacksonville Today. The group would come from the Office of Economic Development, Public Works, the Environmental Quality Division and the Planning Department. Its review would cover the questions listed below, according to the same report.

  • Water supply and wastewater treatment capacity
  • Electrical grid capacity and infrastructure
  • Land use compatibility
  • Utility affordability and reliability for residents
  • Other environmental effects

Why are Peluso and Holder pushing it now?

Peluso pointed to neighboring counties that have already acted. "We've seen other counties proceed with different kinds of moratoriums," he told Jacksonville Today, adding, "We want to make sure that we are not going to be caught unawares." He said possible rules could include land buffers, noise reduction, water-use permit criteria and guardrails for owners who expand step by step, such as a 10-megawatt site that adds 20 megawatts over a decade.

St. Augustine Sailing (sponsored) Sponsored
St. Augustine Sailing (sponsored) Sponsored

Holder has said data centers should get their own land use category in the city's zoning code. At a public meeting she held in October, residents raised concerns about noise, heat, water use and where the buildings would go, Jacksonville Today reported. She said some worry centers could land in "communities that have been historically redlined," and called the bill "an opportunity for us to get it right."

Is a data center actually coming to Jacksonville?

Not a large one so far, based on what JEA has said publicly. At an Oct. 7 meeting called by Holder, JEA said six small data centers operate in its service area, each averaging about 5 megawatts, according to Action News Jax. The utility said it has received at least 50 requests for data center development in recent years but does not currently have the capacity for hyperscale centers, which typically use 50 megawatts or more.

JEA also told council members it is developing a large-load tariff, a pricing policy meant to keep other customers from absorbing the costs if a hyperscale center is built, Action News Jax reported. At a board meeting last week, JEA interim CEO Jody Brooks cited "unprecedented rising costs" for utility materials, with copper up 45% and aluminum up 85% from a year earlier as of Nov. 13, according to Jacksonville Today. Brooks said strain from data center growth elsewhere is part of the reason, even though no data center has landed in JEA's territory.

Does every council member support a pause?

No, at least not yet. At the October meeting, Council member Ron Salem questioned the need for a moratorium because the local grid could not support a large-scale data center anytime soon, Action News Jax reported. Salem instead suggested a committee to study data centers along with other new technologies, such as artificial intelligence and license plate cameras.

What are nearby counties doing?

St. Johns County commissioners voted unanimously Nov. 3 for a one-year moratorium on large data centers that runs through Oct. 31, 2027, according to Jacksonville Today. Nassau County approved its moratorium over the summer, and Clay County also approved a one-year pause. Lake and Volusia counties elsewhere in Florida have passed pauses as well.

Florida law does not let local governments ban data centers outright, Jacksonville Today reported. A state law signed by Gov. Ron DeSantis, SB 484, keeps zoning, permitting and land use decisions under local control, and that includes temporary moratoriums. Gov.-elect Byron Donalds has said he wants to protect taxpayers and the environment on the issue.

What happens next?

Introduction on Tuesday only starts the process, and the bill will go to several council committees before a final vote next year, according to Jacksonville Today. Because the pause would last a full year, it would stretch across both the current council and the council elected in spring 2027. Peluso and Holder are both Democrats running for countywide council seats in that election, Jacksonville Today reported.

Sources: Jacksonville Today (Nov. 3 and Nov. 19, 2026); Action News Jax (Oct. 7, 2026)

Read next · Local Council Delays Plan for HUD Manufactured Homes on 17-Acre Boobie Clark Park

News organizations may republish this story with credit. See our guidelines.

Know which restaurants passed inspection

Get the week's restaurant inspection results every Sunday, This Weekend in Jacksonville every Thursday and each evening's local stories. Free, and you can unsubscribe anytime.

By signing up you agree to get the Jax Times email newsletter. Unsubscribe anytime with one click.

Own a Jacksonville business? Introductory ad rates from $125/month. See ad options Follow Jax Times on FacebookLocal news, events and people, in your feed every day. Follow

Most read this week

  1. 4 Nominees Named for Jacksonville Circuit Judge Vacancy